The gravel is down for the driveway. The electrical service is going
in, as well as the pad for the heating units. We were also able to
frame up the walls for the new bathroom in the historical building.
The Suzuki School of Newton has finally purchased a permanent home for their flourishing music school and preschool. Watch as we grow into our new space!
Friday, October 26, 2018
Monday, October 22, 2018
Lots of Outside Work
A lot of outside work going on this week. The bases for the light
posts are going in, as well as drainage for different areas. The cheek
wall, to stabilize the rubble foundation, was also completed this week.
Friday, October 12, 2018
The new home for Suzuki is coming along!
The window sashes are back on site and are being installed. We have the
riser for the sprinkler system going in. The cheek wall at the
foundation is being poured. And the Brentwood system is in. Another
productive week at Suzuki.
Subscribe to:
Posts (Atom)
April showers bring May flowers
As the showers subside the outside of our gorgeous property is starting to bloom. They are getting ready to plant the sod and this wonderfu...
-
This week we cut through to the 80’s Building from the historical Building, placed the heating units in both buildings, and ran the fire p...
-
It's only a matter of time now before we are finally in our new home. Here are the last of the pictures before you get to see it for yo...
-
The window sashes are back on site and are being installed. We have the riser for the sprinkler system going in. The cheek wall at the f...