Friday, November 2, 2018

Working on the outside of the building

The outside is shaping up at Suzuki.  The parking lot is paved.  Window wells are in.  The dangerous set of stairs have been removed.  Light poles are in place.






Friday, October 26, 2018

This week at Suzuki...

The gravel is down for the driveway.  The electrical service is going in, as well as the pad for the heating units.  We were also able to frame up the walls for the new bathroom in the historical building.






Monday, October 22, 2018

Lots of Outside Work

A lot of outside work going on this week.  The bases for the light posts are going in, as well as drainage for different areas.  The cheek wall, to stabilize the rubble foundation, was also completed this week.  






Friday, October 12, 2018

The new home for Suzuki is coming along!

The window sashes are back on site and are being installed.  We have the riser for the sprinkler system going in.  The cheek wall at the foundation is being poured.  And the Brentwood system is in.  Another productive week at Suzuki.





Friday, September 14, 2018

HVAC Duct work is in!

This week we began installing HVAC ductwork in the attic.  After the walls were framed in the basement, we installed new cast iron drains and in-filled old basement windows with new block.  Next week, we will begin working in the historical building.





Friday, September 7, 2018

The renovations have begun!

The Suzuki School of Newton has just begun renovations and we are eager to share the progress with you!  Please follow us as we progress through this great journey.  We are thrilled to be underway.


















Working on the outside of the building

The outside is shaping up at Suzuki.  The parking lot is paved.  Window wells are in.  The dangerous set of stairs have been removed.  Li...